Project Introduction 

Pingwu Gucheng Hydropower Station is located on upstream trunk of Fu River in the territory of Pingwu County, Sichuan. It is the second grade in Fu River upstream trunk hydropower cascade development, which belongs to low brake water diversion model with two hydropower station installations. Total installed capacity is 100000 kilowatts. Project on Erku left bank in the hydropower station is mainly composed of left bank dam section and water diversion tunnel water inlet. Main construction sections include dam transverse work, overflow dam section and non-overflow dam section with a total of four-hole gate dams. The water inlet belongs to bank tower model. The cavern cross section is round with inner diameter of 9.5 meters.
 

Applied products

Low alkali accelerator; alkali-free accelerator

Case Show

\

3# 4# Dam Section Consolidation Grouting Project in Fujiang Gucheng Hydropower Statio
 

\
 

3# 4# Dam Section Consolidation Grouting Project in Fujiang Gucheng Hydropower Statio